Feeding the transmission stations of the Radio and Television Union

Project total power : 1 Mega Volt Amper (MVA) Project Description 2x500 KVA UPS system (Delphys MX – France origin ) connected as parallel redundant, 30 minutes, backup time with (Exide – Spain origin) battery, with all required panels (Schneider –type tested) and installation had been executed as (Turn-Key) .

Vodafone

Project Total Power : 1 Mega Volt Amper (Mva) Project Description 5x200 Kva UPS System (Delphys Mp Elite – France Origin ), 30 Minutes Backup Time With (Yuassa – UK Origin) Battery, With All Required Panels And Accessories.

Satellite project in NANSC (National Air Navigation Services Company)

Project total power : 1 Mega Volt Amper (MVA) Project Description 5x200 KVA UPS system (Delphys MP elite – France origin ), 30 minutes backup time with (Yuassa – UK origin) battery, with all required panels and accessories.

Borg El-arab Airport

Project Total Power :560kva Project Description: Supply And Install The Following: 2 X200 Kva UPS System (Delphys Mp Elite – France Origin). 2x60 Kva UPS System With Positive Tubular Gel Battery. 2x20kva UPS System. Project Details: All Above Mentioned UPS Systems Connected As (Hot-standby With Isolation Transformers) And Egymatec Executed The Project Including ( Material Factory Inspection, Material Installation, Startup, Commissioning And Site Testing )

Arab Bank data center project at Smart Village

Project Description: Turn Key Data – Center preparation for 124 square Meter as per (Tier 3 clarifications) Project Details: Preparation for Data center room including all civil works (Raised floor, False ceiling, Painting …etc), all the required electro- mechanical requirements such as (UPS redundant, ATS,PDU and all electrical requirements ...) for the Electrical items and (Generator, DX closed control air condition, Fire fighting system ..etc) for the Mechanical items.